Test and commissioning MV/LV power distribution system, substation automation system pada PLTU Asam-Asam 2x60MW.

Fasilitas energi sebagai konteks pengalaman proyek PT GUT.

Project summary

Project register mencatat test and commissioning MV/LV power distribution system, substation automation system pada PLTU Asam-Asam 2x60MW South Kalimantan, dengan end-user PLN, dipesan melalui PT Wijaya Karya.

Work scope

Test and commissioning MV/LV power distribution system, substation automation system.