Substation & Transmission Line
Simangkuk 150kV/275kV Substation Test and Commissioning
Test and commissioning 150kV (2 line bay, 1 trafo bay, 1 bus coupler bay) and 275kV (5 line bay, 1 trafo bay) pada Simangkuk Substation.
Ringkasan proyek
Project register mencatat test and commissioning Simangkuk 150kV/275kV Substation: 150kV (2 line bay; 1 trafo bay; 1 bus coupler bay) dan 275kV (5 line bay; 1 trafo bay), dengan end-user PLN, dipesan melalui PT Siemens Indonesia PTDH.
Scope pekerjaan
Test and commissioning 150kV and 275kV substation.
Kapabilitas terkait
- Electrical