Construction & Commissioning Work for 150kV GIS Senayan III Substation

150kV GIS by Hitachi consist of 2 trafo bays, 2 line bays, 1 coupler bay + bus VT pada Senayan III Substation.

Fasilitas kelistrikan sebagai konteks pengalaman proyek PT GUT.

项目摘要

Project register mencatat construction & commissioning work for 150kV GIS Senayan III Substation, 150kV GIS by Hitachi consist of 2 trafo bays, 2 line bays, 1 coupler bay + bus VT, dengan end-user PT PLN, dipesan melalui PT Hitachi Asia Indonesia.

工作范围

150kV GIS: 2 trafo bays, 2 line bays, 1 coupler bay + bus VT.

相关能力

  • Engineering, Procurement, Construction & Commissioning
  • Electrical