Mining Electrification Batch-2 Distribution System

Design, supply, installation & commissioning of 20kV distribution system mining electrification Batch-2.

Fasilitas kelistrikan sebagai konteks pengalaman proyek PT GUT.

项目摘要

Project register mencatat design, supply, installation & commissioning of 20kV distribution system Mining Electrification Batch-2, dengan end-user PT Adaro, dipesan melalui PT Makmur Sejahtera Wisesa.

工作范围

Design, supply, installation & commissioning of 20kV distribution system.

相关能力

  • Engineering, Procurement, Construction & Commissioning
  • Electrical